10/02/2023 - Capital Financial Performance Report Quarter Three 2022/23 (EX4301)

Resolved that Executive:

·         Note the forecast outturn position on the 2022/23 capital programme.

·         In respect of reprofiling of planned capital expenditure, Executive approve:

(a) £7.3 million of planned expenditure to be reprofiled into financial year 2023/24 (project details in Appendix B).

(b) £39k of Council funding (i.e. debt funding) proposed to be brought forward from approved expenditure for financial year 2023/4 into financial year 2022/23 (project details in Appendix B).

·         In respect of reprofiling of planned capital expenditure, Executive note:

(a) £239k of external funding to be brought forward from financial year 2023/24 into financial year 2022/23 (project details in Appendix B).

 

This decision is eligible to be ‘called-in’.  However, if the decision has not been ‘called-in’ by 5.00pm on 17 February 2023, then it will be implemented.