2025/26 Performance Report Q4

Purpose: to provide assurance that the priority areas in the Council Strategy 2023-2027 are being managed effectively as at the end of the 2025/26 year, and where performance has fallen below the expected level, present information on the remedial action taken and the impact of that action.

Decision:

Resolved that: Executive

·       Noted the progress made in delivering the Council Strategy Delivery Plan 2023-2027 priorities scheduled for this financial year.

·       Reviewed those areas where performance is below target i.e., reporting as ‘Red’ or ‘Amber, and note that the appropriate remedial action is in place.

This decision is not subject to call in as:

·     Report is to note only

therefore it will be implemented immediately.

Minutes:

Councillor Vicky Poole introduced and proposed the 2025/26 Quarter 4 Performance Report (Agenda Item 9). The report provided assurance that the priority areas in the Council Strategy were being managed effectively as at the end of the 2025/26 year and, where performance had fallen below the expected level, presented information on the remedial action taken and the impact of that action.

Councillor Poole pointed out that future reports would use the new reporting measures aligned to the refreshed Council Strategy and this would therefore be the last report covering the existing measures. It was noted that the report had already been considered by the Resources and Place Scrutiny Committee earlier in the week.

Portfolio Holders were invited to comment on the indicators in their own portfolios that were rated red or amber.

Councillor Stuart Gourley outlined progress with permanent pothole repairs over the course of 2025/26. Performance had been at a lower level in Quarter 1, Quarters 2 and 3 were on target, but over the course of the winter months (Quarter 4) it had become more challenging to maintain good performance. Officers had been and would continue to work closely with contractors to make improvements, i.e. to the supply chain, in order to achieve more consistently high performance. Councillor Gourley concluded on this point by highlighting the level of investment into the entire highway network and the improvements achieved as a result.

Councillor Jeff Brooks made reference to the Playing Pitch Strategy measure. While it was reported as being behind schedule in the report, he was able to report that this had been rectified and the current status was that the Strategy was back on schedule.  Beatriz Teixeira confirmed that this was a consequence of the reporting methodology and timeframes. She added that commentary could be inserted into these reports to provide up to date progress where possible, but this would not alter the RAG status.

Councillor Denise Gaines highlighted that the Council was ahead of its affordable homes target for 2030 and further improvements continued to be sought. She added that further affordable homes were scheduled for development.

Councillor Gourley confirmed that the business case for the Grazeley Solar Farm project would be considered by both Scrutiny and the Executive in September 2026.

Councillor Patrick Clark referred to the indicator ‘% of referrals allocated in the previous 12 months without any waiting time (rolling 12 months)’ and explained that performance was 0.5% short of the target of 60%. Councillor Clark added that additional investment was planned in this area in order to try and improve performance.

Councillor Brooks outlined progress with the Corporate Transformation Programme (2.0). He thanked Members of the Transformation Policy Development Group for their work in helping to develop the Programme. The Programme (2.0) would be presented to an extraordinary Executive on 23 July 2026.

Councillor Iain Cottingham advised that the measure to ‘Commission and complete a marketing exercise for Bond Riverside’ had been completed. This was an update from the Quarter 4 position.

Councillor Adrian Abbs felt it would be useful for an additional measure to monitor the underspend against the Community Infrastructure Levy (CIL). He also felt that the measure for the refresh of the Playing Pitch Strategy should be enhanced so that the Faraday Road football pitch was specifically referenced.

RESOLVED that:

·       The progress made in delivering the Council Strategy Delivery Plan 2023-2027 priorities scheduled for this financial year be noted.

·       Reviewed those areas where performance was below target i.e., reporting as ‘Red’ or ‘Amber, had been reviewed, and the remedial action taken noted.