Issue - decisions

*

13/12/2024 - Financial year 2024/25 Quarter Two Capital Financing Performance Report (EX4514)

Resolved that: Executive notes

·         The forecast outturn position of planned expenditure of £60.1 million against the annual budget of £64.9m, creating a forecast £4.8 million underspend.

Executive approves:

·         The proposed reprofiling of planned expenditure from 2024/25 into 2025/26 of £8.1 million, detailed by service in appendix B.

·         The proposed transfer of council funded expenditure budget totalling £0.47 million from 2025/26 into 2024/25 for support of the Playing Pitch action plan.

·         £2.9 million of external funding relating to the Superfast Broad Band project is allocated and the planned project expenditure is funded accordingly.