Three Year Highway Improvement Programme 2025/26 -2027/28

To seek the approval of the Executive Member for Environment and Highways to implement the Draft Three Year Highway Improvement Programme 2025/26 - 2027/28 and proceed with the first year 2025/26 of the programme.

Decision type: Key

Reason Key: Expenditure above £500k and affects more than 1 ward;

Decision status: For Determination

Wards affected: (All Wards);

Notice of proposed decision first published: 15/11/2024

Decision due: 14 Mar 2025 by Portfolio Holder: Environment and Highways

Lead member: Portfolio Holder: Environment and Highways

Lead director: Jon Winstanley - Service Director

Contact: Andrew Reynolds, Principal Engineer (Highways Maintenance) Email: andrew.reynolds@westberks.gov.uk.

Consultation process

Consultation is not normally undertaken as the programme is based on objective data obtained through technical surveys and developed in accordance with the Council's approved Asset Management Plan. However, any comments received from stakeholders during the previous 12 month period are considered and all Local Ward Members and Town/Parish Councils are advised of scheme details in advance of work commencing. The full approved programme will also be published on the Council's website.